Timeline for FirstEnergy Ohio Utilities’ February 2018 PIPP RFP
Delivery Period: June 1, 2018 to May 31, 2019
ActivityDate
Pre-Procurement Activity
Bidder Information SessionWednesday, January 10, 2018
PIPP Supplier Application can be submittedWednesday, January 10, 2018
PIPP Supplier Application is dueFriday, January 26, 2018
Notifications to Registered Bidders including blended SSO price    Thursday, February 01, 2018
February 5, 2018 RFP
Pre-bid security dueFriday, February 02, 2018
Bid window to submit bids (10:00 AM to 02:00 PM ET)Monday, February 05, 2018
CRA notifies the Companies and PUCO of results (tentative)Monday, February 05, 2018
PUCO acceptance of results (tentative)Wednesday, February 07, 2018
Master PIPP Supply Agreement signed (tentative)Friday, February 09, 2018
Power flowFriday, June 01, 2018
2018 Contingency RFP (if necessary)
Pre-bid security dueFriday, February 16, 2018
Bid window to submit bids (10:00 AM to 02:00 PM ET)Tuesday, February 20, 2018
CRA notifies the Companies and PUCO of results (tentative)Tuesday, February 20, 2018
PUCO acceptance of results (tentative)Thursday, February 22, 2018
Master PIPP Supply Agreement signed (tentative)Friday, February 23, 2018
Power flowFriday, June 01, 2018