Timeline for FirstEnergy Ohio Utilities’ February 2020 PIPP RFP
Delivery Period: June 1, 2020 to May 31, 2021
ActivityDate
Pre-Procurement Activity
Bidder Information SessionTuesday, January 14, 2020
PIPP Supplier Application can be submittedTuesday, January 14, 2020
Announcement of blended SSO priceThursday, January 30, 2020
PIPP Supplier Application is dueFriday, January 31, 2020
Notifications to Registered BiddersWednesday, February 5, 2020
February 11, 2020 RFP
Pre-bid security dueFriday, February 7, 2020
Bid window to submit bids (10:00 AM to 02:00 PM ET)Tuesday, February 11, 2020
CRA notifies the Companies and PUCO of results (tentative)Tuesday, February 11, 2020
PUCO acceptance of results (tentative)Wednesday, February 12, 2020
Master PIPP Supply Agreement signed (tentative)Friday, February 14, 2020
Power flowMonday, June 1, 2020
2020 Supplemental RFP (if necessary)
Pre-bid security dueThursday, February 20, 2020
Bid window to submit bids (10:00 AM to 02:00 PM ET) Monday, February 24, 2020
CRA notifies the Companies and PUCO of results (tentative)Monday, February 24, 2020
PUCO acceptance of results (tentative)Wednesday, February 26, 2020
Master PIPP Supply Agreement signed (tentative)Friday, February 28, 2020
Power flowMonday, June 1, 2020