Calendar

Timeline for FirstEnergy Ohio Utilities’ April 2024 PIPP RFP
Delivery Period: June 1, 2024 to May 31, 2025
Activity Date
Pre-Procurement Activity  
Bidder Information Session Thursday, March 7, 2024
PIPP Supplier Application can be submitted Friday, March 8, 2024
Announcement of blended SSO price (tentative) Wednesday, March 20, 2024
PIPP Supplier Application is due Thursday, March 21, 2024
Notifications to Registered Bidders Tuesday, March 26, 2024
April 1, 2024 RFP  
Pre-bid security due Thursday, March 28, 2024
Bid window to submit bids (10:00 AM to 02:00 PM ET) Monday, April 1, 2024
CRA notifies the Companies and PUCO of results (tentative) Monday, April 1, 2024
PUCO acceptance of results (tentative) Wednesday, April 3, 2024
Master PIPP Supply Agreement signed (tentative) Friday, April 5, 2024
Power Flow Saturday, June 1, 2024
2024 Supplemental RFP (if necessary)  
Pre-bid security due Thursday, April 11, 2024
Bid window to submit bids (10:00 AM to 02:00 PM ET) Tuesday, April 16, 2024
CRA notifies the Companies and PUCO of results (tentative) Tuesday, April 16, 2024
PUCO acceptance of results (tentative) Thursday, April 18, 2024
Master PIPP Supply Agreement signed (tentative) Friday, April 19, 2024
Power Flow Saturday, June 1, 2024
 