| | | | CalendarTimeline for FirstEnergy Ohio Utilities’ April 2024 PIPP RFP | Delivery Period: June 1, 2024 to May 31, 2025 | Activity | Date | Pre-Procurement Activity | | Bidder Information Session | Thursday, March 7, 2024 | PIPP Supplier Application can be submitted | Friday, March 8, 2024 | Announcement of blended SSO price (tentative) | Wednesday, March 20, 2024 | PIPP Supplier Application is due | Thursday, March 21, 2024 | Notifications to Registered Bidders | Tuesday, March 26, 2024 | April 1, 2024 RFP | | Pre-bid security due | Thursday, March 28, 2024 | Bid window to submit bids (10:00 AM to 02:00 PM ET) | Monday, April 1, 2024 | CRA notifies the Companies and PUCO of results (tentative) | Monday, April 1, 2024 | PUCO acceptance of results (tentative) | Wednesday, April 3, 2024 | Master PIPP Supply Agreement signed (tentative) | Friday, April 5, 2024 | Power Flow | Saturday, June 1, 2024 | 2024 Supplemental RFP (if necessary) | | Pre-bid security due | Thursday, April 11, 2024 | Bid window to submit bids (10:00 AM to 02:00 PM ET) | Tuesday, April 16, 2024 | CRA notifies the Companies and PUCO of results (tentative) | Tuesday, April 16, 2024 | PUCO acceptance of results (tentative) | Thursday, April 18, 2024 | Master PIPP Supply Agreement signed (tentative) | Friday, April 19, 2024 | Power Flow | Saturday, June 1, 2024 | | | | | |
|
|
|
|
|